We have spoken to the team on-site and they have informed us that the noise incident on Friday 18 October was due to a generator being switched on before 8am.
The piling operators turned on the generator for their work cabin at 7.30am. The site-team informed the operative that this was not permitted and instructed them to turn off the generator until the agreed start time of 8am.
We have reminded the sub-contractors of the set start times and will ensure that this doesn’t happen again. We apologise for any inconvenience caused.