Please see below activities relating to the COLPAI Project, which are due to take place from Monday 20 April.
Monday 20 April – Monday 24 April
Works will include:
Installation of additional welfare units positioned behind the Tower Crane between the boundary wall to London School of Fashion
Service connections to welfare units
Installation of drainage to the School Hall
Air quality monitoring
Environmental monitoring.
Works are not scheduled to take place on Saturday 25 April and Sunday 26 April.
Deliveries
Welfare units
Concrete to the site
6F2 granular fill to the site, which is a mix of crushed concrete, brick and mortar.
On-site security
Security guard now on-site full time 07:00 – 18:30.
CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.
Working Hours Monday to Friday - 08:00 to 18:00 Saturday - 9:00 to 14:00
Consented Reduced Impact Hours During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
Monday to Friday 10:00 to 12:00 and 14:00 to 16:00