Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

Forum

HEALTH & WELLBEING

170 discussions

ESTATE OFFICE ANNOUNCEMENTS

608 discussions

GENERAL COMMENTS & QUERIES

1411 discussions

MAJOR WORKS & PROJECTS

127 discussions

COLPAI

Site of former Richard Cloudesley School

168 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMUNITY CENTRE

21 discussions

ITEMS FOR SALE OR RECYCLE

235 discussions

COLPAI Project Weekly Works Update – W/C Monday 17 August 2020

Dear Neighbour
 
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 17 August 2020.  
 
Monday 17 August – Friday 21 August 
ISG works will include:
  • Construction of Structural Steel Framing System (SFS) for the external walls
  • Continuation of grounds works and drainage
  • Continuation of basement slab to the residential block
  • Continuation of basement liner walls
  • External scaffold to the school building
  • Continuation of brick cladding
  • Installation of drywall
  • Mechanical, electrical and plumbing installation
  • Installation of screed.

Please note, works are not scheduled to take place on Saturday 15 August 2020.
 
Deliveries 
Deliveries taking place throughout the week include:
 
  • Delivery of concrete to the site
  • Delivery of bricks and blocks to the site
  • Delivery of scaffold to the site
  • Delivery of screed to the site.
 
ISG On-Site Security 
 
  • Security guard on-site full time 7am – 6.30pm
  • CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.
 
The City of London Corporation also has CCTV monitoring of the site in place.
 
Working Hours 
Monday to Friday – 8am to 6pm
Saturday – 9am to 2pm
 
Consented Reduced Impact Hours 
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
 
Monday to Friday 10am to 12pm and 2pm to 4pm
 
Noise, dust and vibration monitoring is in place. 
 
Please visit our project website www.colpai-project.co.uk/monitoring-data to view the monthly monitoring data results. Moving forward, we will upload the data on a monthly basis. The monitoring data will also be put up onto the site noticeboard.
 
We have also set up a page on our website to show progress images on-site. To view, please visit https://www.colpai-project.co.uk/progress-onsite. We will update with further images as we move forward.
 
For site emergencies, please contact:
Steven McCarthy, ISG                                                   
T: 07825 719 496