Latest Activity

Sheila replied to Sam's discussion Looking for studio / 1 bed to rent
Monday
An event by Paul Lincoln was featured

Imagine Golden Lane and Community Cafe next Saturday at Under Crescent House

April 27, 2024 from 2pm to 4pm
Saturday
Paul Lincoln posted an event

Imagine Golden Lane and Community Cafe next Saturday at Under Crescent House

April 27, 2024 from 2pm to 4pm
Saturday
Sheila replied to Jax's discussion Looking for a 1 maybe 2 bed on GLE
Apr 19

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

COLPAI Project Weekly Works Update – W/C Monday 6 July 2020


Dear Neighbour
 
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 6 July 2020.  
 
On Monday 6 July 2020, ISG will be removing the crane crawler from site. As the crane is a wide-load, it is subject to a movement order that means it is restricted to travel at certain times. For this reason, the crane crawler will be removed at 8pm. An ISG Construction Manager and traffic marshal will be overseeing the removal and we will ensure that the impact of these works is kept to a minimum.
 
Monday 6 July – Friday 10 July 
ISG works will include:
  • Construction of reinforced concrete superstructure to new school building
  • Construction of Structural Steel Framing System (SFS) for the external walls
  • Continuation of grounds works and drainage
  • Reduced basement dig to residential block
  • External scaffold to the school building
  • Commencement of brick cladding
  • Construction of sewer headings. 
Works are not scheduled to take place on Saturday 4 July 2020. However, there will be an on-site presence with security set-up in the offices this evening (Friday 3 July 2020) and over the weekend. This measure will be in place until ISG has revised its call out arrangements in relation to on-site alarms. ISG will be blocking the windows to the offices to ensure that residents are not disturbed.
 
Deliveries 
Deliveries taking place throughout the week include:
  • Removal of crane crawler from site on Monday 6 July, as noted above
  • Removal of excavated spoil from the site
  • Delivery of concrete to the site
  • Delivery of bricks and blocks to the site. 
ISG On-Site Security
  • Security guard on-site full time 7am – 6.30am
  • CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.
The City of London Corporation also has CCTV monitoring of the site in place.
 
Working Hours 
Monday to Friday – 8am to 6pm
Saturday – 9am to 2pm
 
Consented Reduced Impact Hours 
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
 
Monday to Friday 10am to 12pm and 2pm to 4pm

Noise, dust and vibration monitoring is in place.  Please visit our project website 
www.colpai-project.co.uk/monitoring-data to view the monthly monitoring data results. Moving forward, we will upload the data on a monthly basis. The monitoring data will also be put up onto the site noticeboard. 
 
For site emergencies, please contact:
Steven McCarthy, ISG

T:
 07825 719 496
 

Views: 7

Reply to This

© 2024   Created by Paul Lincoln.   Powered by

Badges  |  Report an Issue  |  Terms of Service