Latest Activity

2 events by Paul Lincoln were featured
13 hours ago
Paul Lincoln posted an event

Being neighbourly in the City of London - Making a Neighbourhood Plan in Barbican and Golden Lane at Barbican Underground Station at street level

May 12, 2024 from 12pm to 2pm
13 hours ago
Paul Lincoln updated an event

Can you repair it? Community Repair Services for Net Zero living at Ralph Perring Centre

May 4, 2024 from 2pm to 4pm
13 hours ago
Steve Watson posted a discussion
yesterday

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

DETAILS OF WORK COST TO THE BLOCK COST TO THE FLAT
At Current Prices At Current Prices
Podium Repairs & Water Proofing

£284,293

£1,804
External/Internal Repairs & Redecoration £163,783 £1,037
Window Replacement £14,536,000 £92,000
Communal Heating Installation £2,907,844 £18,404
Roof Renewal £501,191 £3,172
Landlords Electrical Remedial Works  £629,044 £3,981
 
AGGREGATE AMOUNTS OF ABOVE ESTIMATES £19,022,845 £120,398

Views: 601

Attachments:

Reply to This

Replies to This Discussion

Thanks Alex. What is the source of these numbers?

It is remarkable that we are charged for podium repairs, when the City has without anyone consent turned it into a public square and thoroughfare. 

And then the rest :)

Thanks for sharing. That has gone up nearly 20k since last July. That's roughly a 20% increase in 7 months! The window replacement scheme is out of control. Doesn't bode well for the other blocks on the estate who are being deprioritised in favour of Cresent House.